TENNIS FACILITY AIMS FOR AUGUST OPENING
BY LAVERNE STEWART
STEWART.LAVERNE@DAILYGLEANER.COM
14 JUNE 2012
The Capital Region Community Tennis Centre is expected
to open in early August, says volunteer project director David Clark, after a
series of delays meant it had to push back the planned opening from late July.
“We are really looking forward to getting our
community tennis centre opened,” Clark said.
There are more than 10 contractors working on various
aspects of the construction. All of the construction phases happen
sequentially, Clark said, so when one contractor is delayed it means other
contractors will face delays as well.
A major construction delay happened April 12 when
WorksafeNB issued a stop-work order to Prospect Building Contractors 2004 Ltd.
after one of its workers fell through the roof and landed on the floor, 13
metres (40 feet) below.
In its investigation, WorksafeNB concluded the worker,
a 54-year-old man, wasn’t wearing a safety harness that would have prevented
that fall.
WorksafeNB regional director Melody Mladineo said just
before the man fell, he’d been installing steel sheet roofing and stepped on
the end joint before it was secured. The steel sheet bent and he fell through.
The man’s injuries to his ankle, leg and pelvis were
described by WorksafeNB as serious.
In his legal career, Clark said, he works on
construction teams throughout North America. Any time a worker comes to work
and doesn’t go home that day because of an injury, he said, is a bad day.
“We are not pleased that this happened on our project
... We very much monitored the condition of the worker and I understand he’s
going to make a complete recovery, which we are very thankful for.”
The stop-work order against Prospect Building
Contractors 2004 Ltd. continued until WorksafeNB carried out its investigation.
On May 28, the stop-work order was lifted after WorksafeNB was satisfied the
company had proven fall-prevention equipment is now being used by its workers.
“We are disappointed that this contractor has not
moved ahead a little faster, but we have had excellent co-operation from the
other contractors,” Clark said. “I am told this contractor is very much on side
to finish their part of the work within the next week or so.”
All of the contractors involved in this project, he
said, have been accommodating about this delay.
“They could have probably made claims against our
organization, and they chose not to because we have worked corroboratively with
them and they see us as a non-profit community organization that (is) trying to
do something good for the community.”
The stop-work order, Clark said, had a limited impact on
other work because it involved a small area of the roof. While that stop-work
order was in place, contractors working on other parts of the building were
able to go ahead with their work.
During that time, the mechanical system that connects
with the geothermal heating plant at the Grant-Harvey Complex was installed.
Paving was applied to the interior of the building last week, the offices and
viewing area of the facility are 75 per cent complete, and it’s expected the
building will be fully enclosed within the next week and a half, he said.
There have been other delays, too. The construction
company responsible for the building’s exterior had crews working on other
sites around the province. It’s now concentrating its efforts on the tennis
centre site and is pushing to complete the work.
“Last week you will have noticed one of the walls
along the side was completed,” Clark said. “As we speak today, they would be
working on the roof of the facility.”
This building has a high level of insulation because of
the geothermal system. No work can be done on the roof if there is any moisture
in the air. Because of the nature of the panels being installed, which are
sensitive to wind, there are also restrictions when people can work on the
roof, he said.
“The weather looks like it’s going to co-operate for
the next seven to 10 days.”
The Capital Region Tennis Association, he said, isn’t
considering financial penalties against contractors for not completing the
project on time.
“It’s my view that if we can do this without having to
resort to any form of sanction against anyone, it’s the best solution for the
project and for the community,” he said. “Will I say never? No ... There is
really no upside to (penalties) unless it gets to a point that we are looking
at a very long delay. I just don’t see that in the cards.”
Senior representatives of Tennis Canada visited the
site last weekend to see the construction progress. Fundraising efforts are
continuing to come up with the final $300,000 needed to complete this $2.4-million
facility.
Clark said the association is grateful the city has
provided it with a land lease at no cost, as well as the provision of in-kind
support. Without all of this, he said, it would have cost somewhere between $3
million and $4 million.
“The financial situation we find ourselves in is
awesome and we are confident we are going to close our last $300,000 in our
fundraising,” Clark said.
No comments:
Post a Comment